TRANSOCEAN DEEPWATER PATHFINDER

After successfully completing flooring & living quarters upgrades on several Transocean rigs – and the drillship Discoverer Spirit, PCS was selected to perform IMO flooring repairs on Deepwater Pathfinder.

  • Project size: 800 SF
  • Project specs: remove and replace existing floor coverings and underlayment that failed due to moisture intrusion
  • Existing floor finishes: ceramic tile and sheet vinyl
  • Areas upgraded: laundry room and medic area

Key Considerations for the project included the following:
Maintenance/Safety: Transocean needed to upgrade to a flooring system that would minimize future moisture intrusion and therefore provide a longer life span.

IMO Approvals: The new flooring system needed to be IMO and U.S. Coast Guard approved.

Project Timeline: This project needed to be completed in the least amount of time possible since the laundry room would be shut down during the flooring upgrade.

Construction Management: Transocean preferred a turnkey upgrade service for the complete removal and installation of flooring in the specified areas. PCS partnered with Stallion Offshore to provide a temporary laundry unit.

Marine Decking Products Used:

  • PolySpec® IMO Waterproofing Membrane
  • PolySpec® FLEX IMO – IMO Approved Flexible Decorative Chip Seamless Floor